Do you have a solution for upgrading an existing lath and plaster ceiling for 60 minutes where I can leave it in place?

When upgrading an existing lath and plaster or an existing plasterboard ceiling from below; a layer of 12mm thick Supalux® board can be used to provide up to 60 minutes fire resistance without removing the existing ceiling. For details, please see page 113 (Fig 4.20.2) Chapter 4: Ceiling, Floors and Roofs for more details. 

 

 